Downtown is just the first stage of the public transportation project. It will be city-wide by 2016
"Basically what we plan to do is have smaller vehicles that go into neighborhoods and collect the people and bring them to these main lines.
Each stage will cost an average of $18 million and will take approximately a year to complete.
* Downtown enhancements - $12 million
* North corridor - $18 million
* Southeast corridor - $16 million
* Southwest corridor - $19 million
* East corridor - $25 million
The grand total will be $90 million, according to JTA.